Shoreline cleanup – September 21, 2011
-
Shoreline cleanup – November 8, 2011
-
Dock walkway construction – November 29, 2011
-
Dock attachment to sea wall - December 6, 2011
-
Restoring a roof – December 7, 2011
-
Dock roof work continues – December 8, 2011
-
Non slip surface installed on gangway – December 8, 2011
-
New support posts being erected – December 9, 2011
-
Roof support posts being installed – December 15, 2011
-
Connecting the vertical roof supports with horizontal cross members – December 23, 2011
-
Adding roof horizontal braces to vertical support posts – January 05, 2012
-
First snow, no work today – January 12, 2012
-
Repairing floats – January 16, 2012
-
New stantions connecting dock to seawall – January 24, 2012
-
New section (4 slips) installed on dock #6 – January 26, 2012
-
No work today – February 13, 2012
-
Roofs going up – February 14, 2012
-
Roof work continues. Looking good – February 15, 2012
|